Construction of a wind farm with a capacity of 25 MW in the Vitebsk region, Liozno district, near the village of Veleshkovichi
Enterprise and its description
Limited Liability Company "VES Veleshkovichi"
Products, services description (detailed, indicating CN FEA code)Electric Energy
Project description
Project in progress
Total volume of investments, thousand $45900
Expected input of an investor, thousand $6960
Project period2021-2023
Investor participation formnew enterprise
Project descriptionConstruction of a wind farm by installing wind power plants (6 wind turbines) with a total capacity of about 25 MW. The generated electricity will be supplied to the general power supply network of the region.
The nomenclature of the product to be produced with indication of the CN FEA codeelectric Energy
Volume of investments, thousand $45900
Annual revenues once fully operational (without VAT, thousand $)8998
Dymanic pay-back period, yrs13.9
IRR, %5.96
Potential customerorganizations and individuals of the Republic of Belarus
Key benefits of the projectSocial and economic effect of the investment project: - production of environmentally friendly electricity in compliance with the maximum international environmental requirements; - Increasing the revenues of the local and republican budgets through the payment of taxes; - reduction of emissions of CO2 and other harmful substances into the atmosphere; - creation of new jobs for the period of construction and for the period of operation of the facility; - participation in the construction of Belarusian contractors
Level of project development: feasibility study, business-plan (indicating the date of development), pre-investment study, design estimate documentation, construction work in progress etc.A detailed project plan and its business model have been developed, an act has been obtained for choosing the location of a land plot for construction, the process of land acquisition and the establishment of boundaries for construction has been carried out, land lease agreements have been concluded, state registration of land plots has been carried out, permission has been obtained for design and survey work and construction, an architectural design has been developed, positive conclusions from state environmental and construction expertise have been obtained, an optimal scheme for connecting a wind farm to the network has been calculated, contracts have been concluded and are being implemented with relevant organizations.
Avaliability of land plot for project implementationAvaliability of land for project realization